Station Construction Underway at Bakerview-166 Street Station

Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026.

Access to businesses and the Surrey Sport and Leisure Centre will be maintained via 166 Street and 84 Avenue.

View detailed notice

If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.