Posted October 3, 2025 – This is an update to the notice distributed on September 10, 2025, to reflect the addition of Saturday work. Construction of the elevated guideway on Industrial Avenue (west of the 203 Street intersection) is underway. To support this work, from September 17 until mid-October, large cranes and drill rigs will be in the area completing intermittent piling over six weeks. An increase in noise, vibration, and dust is expected.
Construction on this portion of the elevated guideway is anticipated through summer 2026. Access to/from 5735 203 Street is available via 203 Street.
There are additional activities on Industrial Avenue that are not reflected in this notice. A list of current notices can be found under each station area on our Current Work page. For information about current traffic pattern changes on Industrial Avenue, please review the notices under Langley City Centre Station.