Current construction information, including notifications of upcoming work, is posted below.

Major construction on the SkyTrain extension is underway. We are currently focused on utility work, vegetation management, roadworks, foundation construction, and other related activities.

People who travel on Fraser Highway should plan additional travel time or consider alternative routes, as work is taking place in multiple locations along the corridor. You can continue to access businesses, services and residences along Fraser Highway and Industrial Avenue throughout construction.

Please see notifications below and contact us if you have specific questions about what’s happening currently on and near the project alignment. Sign up to receive project updates and construction notices.

Note: Drones will be used throughout the duration of the Surrey Langley SkyTrain Project to monitor and document project work, with no intention of collecting personal information. Please see our related FOIPPA notice on the use of drones.

Current Work Areas

The Surrey Langley SkyTrain project work areas have been identified to correspond with the future SkyTrain stations. View our station map to see each station location and find project notifications by station area posted below.

Station map showing where each of the new eight stations will be in Surrey and Langley.
An image showing traffic pattern changes.
  • Weekly Traffic Advisory: January 20 – January 26

    Posted January 17, 2025 – This advisory outlines traffic pattern changes from January 20, 2025 – January 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are…

    Read more

  • Weekly Traffic Advisory: January 13 – January 19

    Posted January 10, 2025 – This advisory outlines traffic pattern changes from January 13, 2025 – January 19, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are…

    Read more

  • Weekly Traffic Advisory: January 6 – January 12

    Posted January 3, 2025 – This advisory outlines traffic pattern changes from January 6, 2025 – January 12, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are…

    Read more

  • Weekly Traffic Advisory: December 23 – January 5

    Posted December 20, 2024 – This advisory outlines traffic pattern changes from December 23, 2024 – January 5, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are…

    Read more

  • Weekly Traffic Advisory: December 16 – December 22

    Posted December 13, 2024 – This advisory outlines traffic pattern changes during the week of December 16 – December 22, 2024 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and…

    Read more

A rendering of the future Green Timbers Station.
  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • Notice of work on 140 Street and Fraser Highway

    Posted September 5, 2024 – Hydrovac work will take place on 140 Street and Fraser Highway on September 9 and September 10. The hydrovac work requires a single lane closure northbound for the trucks and…

    Read more

  • Site preparations for upcoming construction

    Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

A rendering of the future 152 Street Station.
  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • Traffic Update: Fraser Highway between 148 and 152 Street

    Posted October 9, 2024 – Travel lanes, pedestrian, and cycling lanes will be adjusted on Fraser Highway between 148 Street and 152 Street. There will be intermittent lane closures on the approach to the intersection…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • Vegetation management at 15079 Fraser Highway

    Posted August 22, 2024 – Vegetation management activities, including tree removal, will take place at 15079 Fraser Highway. This location is a future site office that will accommodate staff and workers of SkyLink Guideway Partners.…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

A rendering of the future Fleetwood Station
  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • UPDATED: Traffic Update: Fraser Highway between 162 Street and 164 Street

    Posted December 19, 2024 – To support utility work, traffic pattern changes will be in effect until late January 2025. There will be a work pause in late December where traffic control measures will be removed.…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

A rendering of the future Bakerview-166 Street Station.
  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • UPDATED: Traffic Update: Fraser Highway between 162 Street and 164 Street

    Posted December 19, 2024 – To support utility work, traffic pattern changes will be in effect until late January 2025. There will be a work pause in late December where traffic control measures will be removed.…

    Read more

  • Traffic Update: 166 Street and Fraser Highway Intersection

    Posted November 29, 2024 – During upcoming utility work, there will be temporary traffic pattern changes at the intersection of 166 Street and Fraser Highway. Traffic pattern changes are expected to begin December 2, 2024,…

    Read more

  • UPDATED: Traffic Update – Fraser Highway between Highway 15 and 184 Street

    Posted November 14, 2024 – The work previously planned to start mid-November is being rescheduled for late-November. Vehicle travel lanes on Fraser Highway between Highway 15 (176 Street) and 184 Street will be shifted south and…

    Read more

  • UPDATED: Traffic Pattern and Project Update – Fraser Highway and 166 Street

    Posted November 7, 2024 – The work previously planned to start mid-November is being rescheduled for December 2024.  This is an update of the notification from October 21, 2024. View detailed notice If you have…

    Read more

A rendering of the future Hillcrest-184 Street Station.
  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

A rendering of the future Clayton Station.
  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

A rendering of the future Willowbrook Station.
  • Demolition work at 6000 Production Way

    Posted June 26, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of an existing structure, including utility disconnections, tree removal, hazardous material abatement and…

    Read more

A rendering of the future Langley City Centre Station.
  • Notice of Evening Work Near 201A Street and Industrial Avenue

    To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the site where the future 201 Street Propulsion Power Substation (PPS) will be located. A PPS supplies electrical power to…

    Read more

  • Notice of Evening Work Near 203 Street and Acacia Crescent

    To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the property where the future Langley City Centre Station will be located. Materials for gravel surface treatment work will be…

    Read more

  • Demolition work at 6000 Production Way

    Posted June 26, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of an existing structure, including utility disconnections, tree removal, hazardous material abatement and…

    Read more