Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: October 5 to October 11, 2026

    Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 28 to October 4, 2026

    Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 21 to September 27, 2026

    Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 14 to September 20, 2026

    Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 7 to September 13, 2026

    Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Access change 138 Street north of Fraser Highway

    Posted October 28, 2026 – this is an update to the notice posted on October 5, 2026. There will be no vehicle access to/from 138 Street north of Fraser Highway until mid-December 2026. Cyclist and…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 152 Street

    Posted October 16, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at the future 152 Street Station. To carry out this work, extended hours will be in effect on October 20 and…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 160 Street

    Posted October 7, 2026 – Surrey Langley SkyTrain construction is progressing, including concrete pours and concrete work at the future Fleetwood Station. To carry out this work, extended hours will be in effect on October…

    Read more

  • Traffic Update: No access to 162 Street north of Fraser Highway

    Posted September 17, 2026 – Surrey Langley SkyTrain construction is progressing, including road restoration activities. To support this work, there will be no access to/from 162 Street north of Fraser Highway in effect 24/7 from…

    Read more

  • Traffic Update: No access to Fleetwood Way from Fraser Highway

    Posted September 9, 2026 – A launching gantry will be active in this area installing the guideway. No access to/from Fleetwood Way and Fraser Highway from September 12 to 16, 2026 from 7 a.m. to…

    Read more

  • Traffic Update: Overnight closure of Highway 15 at Fraser Highway

    Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…

    Read more

  • Traffic Update: Access change on 166 Street north of Fraser Highway

    Posted March 5, 2026 – To support utility installations, there will be no access to the Surrey Sport & Leisure Complex from the north end of 166 Street starting March 9, 2026, for up to…

    Read more

  • Station Construction Underway at Hillcrest-184 Street Station

    Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated.  View detailed notice…

    Read more

  • Station Construction Underway at Bakerview-166 Street Station

    Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…

    Read more

  • Traffic Update: Access change on 166 Street and Fraser Highway

    Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…

    Read more

  • Traffic Update: Closure of 68 Avenue North of Fraser Highway

    Posted April 10, 2025 – To support ongoing SkyTrain construction, there will be a closure at 68 Avenue North of Fraser Highway from April 22, 2025, to April 25, 2025. The travelling public can expect…

    Read more

  • Traffic Update: Utility locate activities on Langley Lane (Laneway east of Fraser Highway and south of Highway 10)

    Posted March 27, 2025 – Activities include early works to prepare for construction of the future SkyTrain, including foundation and guideway construction. Single lane alternating traffic will be in effect. Traffic control personnel will be…

    Read more

  • Construction Activities: Industrial Avenue between 200 Street and 203 Street

    Posted March 14, 2025 – Preliminary activities will occur intermittently on Industrial Avenue from 200 Street to 203 Street from March 19, 2025 through spring 2025. Activities include survey work, utility investigation and vegetation management.…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

  • Traffic Update: Fraser Highway between 196 Street and Highway 10

    Posted March 7, 2025 – Activities will include roadwork, installing construction fencing around work areas, moving existing utilities to allow for construction and installing new utilities to supply power for the future SkyTrain. Foundation construction…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.