Weekly Traffic Advisory: October 5 to October 11, 2026
Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 28 to October 4, 2026
Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 21 to September 27, 2026
Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 14 to September 20, 2026
Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 7 to September 13, 2026
Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Traffic Update: No access to 162 Street north of Fraser Highway
Posted September 17, 2026 – Surrey Langley SkyTrain construction is progressing, including road restoration activities. To support this work, there will be no access to/from 162 Street north of Fraser Highway in effect 24/7 from…
-
Traffic Update: No access to Fleetwood Way from Fraser Highway
Posted September 9, 2026 – A launching gantry will be active in this area installing the guideway. No access to/from Fleetwood Way and Fraser Highway from September 12 to 16, 2026 from 7 a.m. to…
-
UPDATED: Overnight closure and extended hours on Fraser Highway between 140 Street and 96 Avenue
This is an update to the notice distributed on June 29, 2026. This notice provides details of upcoming overnight construction to support the Surrey Langley SkyTrain. Fraser Highway will be fully closed between 140 Street and 96 Avenue from July 6…
-
Traffic Update: Overnight closure on Fraser Highway between 140 Street and 96 Avenue
Posted June 29, 2026 – This notice provides details of upcoming overnight construction to support the Surrey Langley SkyTrain. Fraser Highway will be fully closed between 140 Street and 96 Avenue from July 6 to…
-
UPDATE: Overnight closures on Fraser Highway between 140 Street and 148 Street
Posted June 12, 2026 – Overnight closure on Fraser Highway for SkyTrain construction from 9 p.m. to 5:30 a.m. June 10 and June 11, 2026 and 9 p.m. to 5:30 a.m. June 12, 14 and 15, 2026. Pedestrian and…
-
Traffic Update: Single lane alternating traffic on Fraser Highway at 184 Street
Posted September 9, 2026 – To support box beam installation work, temporary traffic pattern changes will be in effect on September 11, 2026. Lane reductions on the approach to the intersection on 184 Street. Single…
-
Extended Hours: Fraser Highway east of Highway 15
Posted May 12, 2026 – Extended work hours will be in effect from 10 p.m. to 7 a.m., May 19 to May 22, 2026, to support Surrey Langley SkyTrain construction. Overnight work is required to…
-
Traffic Update: Overnight closure of Highway 15 at Fraser Highway
Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…
-
Traffic Update: Access change on 166 Street north of Fraser Highway
Posted March 5, 2026 – To support utility installations, there will be no access to the Surrey Sport & Leisure Complex from the north end of 166 Street starting March 9, 2026, for up to…
-
Station Construction Underway at Hillcrest-184 Street Station
Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated. View detailed notice…
-
Geotechnical Investigation on Industrial Ave
Posted October 10, 2024 – Geotechnical investigation to gather information about ground conditions for the future location of piers will occur on Industrial Avenue, starting October 16 for approximately two weeks. There will be parking…
-
Site preparations for upcoming construction
Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…
-
UPDATED: Various works along Fraser Highway between 140 & 192 Street
Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…
-
UPDATED: Lane and Parking Impacts Around 203 Street, Industrial Avenue and Acacia Crescent
Posted August 8, 2024 – This is an update of the notification from July 30, 2024 as dates of work have changed. Crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and…
-
Lane Reduction on 203 Street, 203A Street and Acacia Crescent
Posted July 24, 2024 – To prepare for construction of the Surrey Langley SkyTrain, crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and the 201 Street Propulsion Power Substation (PPS)…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.