Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: February 3 – February 9
Posted January 31, 2025 – This advisory outlines traffic pattern changes from February 3, 2025 – February 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: January 27 – February 2
Posted January 24, 2025 – This advisory outlines traffic pattern changes from January 27, 2025 – February 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: January 20 – January 26
Posted January 17, 2025 – This advisory outlines traffic pattern changes from January 20, 2025 – January 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: January 13 – January 19
Posted January 10, 2025 – This advisory outlines traffic pattern changes from January 13, 2025 – January 19, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: January 6 – January 12
Posted January 3, 2025 – This advisory outlines traffic pattern changes from January 6, 2025 – January 12, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
UPDATED: Access change 138 Street north of Fraser Highway
Posted October 28, 2026 – this is an update to the notice posted on October 5, 2026. There will be no vehicle access to/from 138 Street north of Fraser Highway until mid-December 2026. Cyclist and…
-
Construction Update: Extended hours at Fraser Highway and 152 Street
Posted October 16, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at the future 152 Street Station. To carry out this work, extended hours will be in effect on October 20 and…
-
Construction Update: Extended hours at Fraser Highway and 160 Street
Posted October 7, 2026 – Surrey Langley SkyTrain construction is progressing, including concrete pours and concrete work at the future Fleetwood Station. To carry out this work, extended hours will be in effect on October…
-
Traffic Update: No access to 162 Street north of Fraser Highway
Posted September 17, 2026 – Surrey Langley SkyTrain construction is progressing, including road restoration activities. To support this work, there will be no access to/from 162 Street north of Fraser Highway in effect 24/7 from…
-
Traffic Update: No access to Fleetwood Way from Fraser Highway
Posted September 9, 2026 – A launching gantry will be active in this area installing the guideway. No access to/from Fleetwood Way and Fraser Highway from September 12 to 16, 2026 from 7 a.m. to…
-
Piling activities at various locations on Fraser Highway
Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…
-
Demolition work at 18543 and 18565 Fraser Highway
Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…
-
Demolition Work at 8215 166 Street and Fraser Highway
Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…
-
Traffic Update: No access to 203 Street from Industrial Avenue
Posted October 22, 2026 — To support concrete work and track installation on a portion of the elevated guideway on Industrial Avenue, a daytime closure between 201A Street and 203 Street is required on October…
-
UPDATED: Temporary intersection closure and extended hours at Industrial Avenue and 203 Street
Posted September 28, 2026 – This is an update to the notice posted on September 14, 2026. To support concrete work and concrete pours on a portion of the elevated guideway on Industrial Avenue and over…
-
UPDATED: No access to 188 Street from Fraser Highway
Posted September 15, 2026 – This is an update to the notice posted on September 11, 2026. No access to/from 188 Street and Fraser Highway September 25, 28, 29, and October 1 and 2, 2026 from 7 a.m.…
-
UPDATED: Extended hours and no access to Willowbrook Drive/196 Street north of Fraser Highway
Posted September 22, 2026 – This is an update to the notice posted on September 10, 2026. To support guideway installation, the following traffic pattern changes will be in effect from September 24 to 26,…
-
UPDATED: Traffic Update: Pedestrian access change between 62A Avenue and Fraser Highway
Posted September 1, 2026 – This is an update to the notice posted on August 19, 2026. To support guideway installation as the launching gantry moves east, a pedestrian access change will be in effect until September…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found