  • Weekly Traffic Advisory: October 5 to October 11, 2026

    Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 28 to October 4, 2026

    Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 21 to September 27, 2026

    Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 14 to September 20, 2026

    Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 7 to September 13, 2026

    Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: No access to 162 Street north of Fraser Highway

    Posted September 17, 2026 – Surrey Langley SkyTrain construction is progressing, including road restoration activities. To support this work, there will be no access to/from 162 Street north of Fraser Highway in effect 24/7 from…

    Read more

  • Traffic Update: No access to Fleetwood Way from Fraser Highway

    Posted September 9, 2026 – A launching gantry will be active in this area installing the guideway. No access to/from Fleetwood Way and Fraser Highway from September 12 to 16, 2026 from 7 a.m. to…

    Read more

  • UPDATED: Overnight closure and extended hours on Fraser Highway between 140 Street and 96 Avenue

    This is an update to the notice distributed on June 29, 2026. This notice provides details of upcoming overnight construction to support the Surrey Langley SkyTrain. Fraser Highway will be fully closed between 140 Street and 96 Avenue from July 6…

    Read more

  • Traffic Update: Overnight closure on Fraser Highway between 140 Street and 96 Avenue

    Posted June 29, 2026 – This notice provides details of upcoming overnight construction to support the Surrey Langley SkyTrain. Fraser Highway will be fully closed between 140 Street and 96 Avenue from July 6 to…

    Read more

  • UPDATE:  Overnight closures on Fraser Highway between 140 Street and 148 Street

    Posted June 12, 2026 – Overnight closure on Fraser Highway for SkyTrain construction from 9 p.m. to 5:30 a.m. June 10 and June 11, 2026 and 9 p.m. to 5:30 a.m. June 12, 14 and 15, 2026. Pedestrian and…

    Read more

  • Traffic Update: Single lane alternating traffic on Fraser Highway at 184 Street

    Posted September 9, 2026 – To support box beam installation work, temporary traffic pattern changes will be in effect on September 11, 2026. Lane reductions on the approach to the intersection on 184 Street. Single…

    Read more

  • Extended Hours: Fraser Highway east of Highway 15

    Posted May 12, 2026 – Extended work hours will be in effect from 10 p.m. to 7 a.m., May 19 to May 22, 2026, to support Surrey Langley SkyTrain construction. Overnight work is required to…

    Read more

  • Traffic Update: Overnight closure of Highway 15 at Fraser Highway

    Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…

    Read more

  • Traffic Update: Access change on 166 Street north of Fraser Highway

    Posted March 5, 2026 – To support utility installations, there will be no access to the Surrey Sport & Leisure Complex from the north end of 166 Street starting March 9, 2026, for up to…

    Read more

  • Station Construction Underway at Hillcrest-184 Street Station

    Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated.  View detailed notice…

    Read more

  • Traffic Update: No access to 68 Avenue north of Fraser Highway

    Posted August 18, 2026 – To support the installation of a new traffic signal and road restoration work, temporary traffic pattern changes will be in effect from August 24 to September 1, 2026. No access…

    Read more

  • UPDATED: Closure of 64 Avenue north of Fraser Highway

    Posted July 20, 2026 – This is an update to the notice distributed on July 8, 2026. To support Surrey Langley SkyTrain guideway installation, access to and from 64 Avenue north of Fraser Highway will be…

    Read more

  • Traffic Update: 201A Street between Fraser Highway and Industrial Avenue

    Posted July 17, 2026 – To support the installation of new utilities to power the future SkyTrain, traffic pattern changes will be in effect from July 23 to August 15, 2026. Entry and exit to…

    Read more

  • UPDATED: Closure of 64 Avenue north of Fraser Highway

    Posted July 15, 2026 – This is an update to the notice distributed on July 8, 2026. To support Surrey Langley SkyTrain guideway installation, access to and from 64 Avenue north of Fraser Highway will be…

    Read more

  • Traffic Update: Closure of 64 Avenue north of Fraser Highway

    Posted July 8, 2026 – To support Surrey Langley SkyTrain guideway installation, access to and from 64 Avenue north of Fraser Highway will be restricted from July 14 to 17, 2026, during construction hours (7…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.