  • Weekly Traffic Advisory: February 17 – February 23

    Posted February 14, 2025 – This advisory outlines traffic pattern changes from February 17, 2025 – February 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 10 – February 16

    Posted February 7, 2025 – This advisory outlines traffic pattern changes from February 10, 2025 – February 16, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 3 – February 9

    Posted January 31, 2025 – This advisory outlines traffic pattern changes from February 3, 2025 – February 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 27 – February 2

    Posted January 24, 2025 – This advisory outlines traffic pattern changes from January 27, 2025 – February 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 20 – January 26

    Posted January 17, 2025 – This advisory outlines traffic pattern changes from January 20, 2025 – January 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • Vegetation management at 15079 Fraser Highway

    Posted August 22, 2024 – Vegetation management activities, including tree removal, will take place at 15079 Fraser Highway. This location is a future site office that will accommodate staff and workers of SkyLink Guideway Partners.…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition Work Continues Adjacent to Fraser Highway Near 152 Street

    Posted August 14, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other miscellaneous activities, will continue to take place adjacent to Fraser Highway near 152 Street in the coming…

    Read more

  • Construction Update: Extended hours at Bakerview-166 Street Station

    Posted November 6, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at Bakerview-166 Street Station. To carry out this work, extended hours will be in effect on Monday, November 9, 2026, from…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations

    Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…

    Read more

  • UPDATED: No access to 182 Street south of Fraser Highway

    Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…

    Read more

  • Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street

    Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…

    Read more

  • Construction Activities: Industrial Avenue between 200 Street and 203 Street

    Posted March 14, 2025 – Preliminary activities will occur intermittently on Industrial Avenue from 200 Street to 203 Street from March 19, 2025 through spring 2025. Activities include survey work, utility investigation and vegetation management.…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

  • Traffic Update: Fraser Highway between 196 Street and Highway 10

    Posted March 7, 2025 – Activities will include roadwork, installing construction fencing around work areas, moving existing utilities to allow for construction and installing new utilities to supply power for the future SkyTrain. Foundation construction…

    Read more

  • UPDATED: Traffic Update: 203 Street and 203A Street

    Posted February, 20, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…

    Read more

  • Traffic Update: 203 Street and 203A Street

    Posted February 10, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.