  • Weekly Traffic Advisory: February 3 – February 9

    Posted January 31, 2025 – This advisory outlines traffic pattern changes from February 3, 2025 – February 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 27 – February 2

    Posted January 24, 2025 – This advisory outlines traffic pattern changes from January 27, 2025 – February 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 20 – January 26

    Posted January 17, 2025 – This advisory outlines traffic pattern changes from January 20, 2025 – January 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 13 – January 19

    Posted January 10, 2025 – This advisory outlines traffic pattern changes from January 13, 2025 – January 19, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 6 – January 12

    Posted January 3, 2025 – This advisory outlines traffic pattern changes from January 6, 2025 – January 12, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition Work Continues Adjacent to Fraser Highway Near 152 Street

    Posted August 14, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other miscellaneous activities, will continue to take place adjacent to Fraser Highway near 152 Street in the coming…

    Read more

  • Demolition work at 16039 Fraser Highway

    Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…

    Read more

  • Demolition work at various locations near Fraser Hwy

    To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • UPDATED: No access to 182 Street south of Fraser Highway

    Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…

    Read more

  • Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street

    Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…

    Read more

  • Traffic Update: Single lane alternating traffic on Fraser Highway at 184 Street

    Posted September 9, 2026 – To support box beam installation work, temporary traffic pattern changes will be in effect on September 11, 2026. Lane reductions on the approach to the intersection on 184 Street. Single…

    Read more

  • Extended Hours: Fraser Highway east of Highway 15

    Posted May 12, 2026 – Extended work hours will be in effect from 10 p.m. to 7 a.m., May 19 to May 22, 2026, to support Surrey Langley SkyTrain construction. Overnight work is required to…

    Read more

  • UPDATED: Traffic Update: 203 Street and 203A Street

    Posted February, 20, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…

    Read more

  • Traffic Update: 203 Street and 203A Street

    Posted February 10, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…

    Read more

  • Traffic Update: Fraser Highway between 64 Avenue and 196 Street

    Posted February 5, 2025 – Vehicle travel lanes on Fraser Highway between 64 Avenue and 196 Street/Willowbrook Drive will be reduced to single lanes westbound and eastbound. Traffic pattern changes will be in effect from…

    Read more

  • UPDATED: Test piling activities at Industrial Ave and 203 Street

    Posted November 19, 2024 – Test piling is now scheduled to begin November 20. There will be a temporary increase in noise and vibration while this work is taking place. This is an update of the…

    Read more

  • Geotechnical Investigation on Industrial Ave

    Posted October 10, 2024 – Geotechnical investigation to gather information about ground conditions for the future location of piers will occur on Industrial Avenue, starting October 16 for approximately two weeks. There will be parking…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.