Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: October 5 to October 11, 2026

    Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 28 to October 4, 2026

    Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 21 to September 27, 2026

    Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 14 to September 20, 2026

    Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 7 to September 13, 2026

    Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition Work Continues Adjacent to Fraser Highway Near 152 Street

    Posted August 14, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other miscellaneous activities, will continue to take place adjacent to Fraser Highway near 152 Street in the coming…

    Read more

  • Demolition work at 16039 Fraser Highway

    Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…

    Read more

  • Demolition work at various locations near Fraser Hwy

    To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • UPDATED: No access to 182 Street south of Fraser Highway

    Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…

    Read more

  • Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street

    Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…

    Read more

  • Traffic Update: Single lane alternating traffic on Fraser Highway at 184 Street

    Posted September 9, 2026 – To support box beam installation work, temporary traffic pattern changes will be in effect on September 11, 2026. Lane reductions on the approach to the intersection on 184 Street. Single…

    Read more

  • Extended Hours: Fraser Highway east of Highway 15

    Posted May 12, 2026 – Extended work hours will be in effect from 10 p.m. to 7 a.m., May 19 to May 22, 2026, to support Surrey Langley SkyTrain construction. Overnight work is required to…

    Read more

  • Traffic Update: No access to 203 Street from Industrial Avenue

    Posted October 22, 2026 — To support concrete work and track installation on a portion of the elevated guideway on Industrial Avenue, a daytime closure between 201A Street and 203 Street is required on October…

    Read more

  • UPDATED: Temporary intersection closure and extended hours at Industrial Avenue and 203 Street

    Posted September 28, 2026 – This is an update to the notice posted on September 14, 2026. To support concrete work and concrete pours on a portion of the elevated guideway on Industrial Avenue and over…

    Read more

  • UPDATED: No access to 188 Street from Fraser Highway

    Posted September 15, 2026 – This is an update to the notice posted on September 11, 2026. No access to/from 188 Street and Fraser Highway September 25, 28, 29, and October 1 and 2, 2026 from 7 a.m.…

    Read more

  • UPDATED: Extended hours and no access to Willowbrook Drive/196 Street north of Fraser Highway

    Posted September 22, 2026 – This is an update to the notice posted on September 10, 2026. To support guideway installation, the following traffic pattern changes will be in effect from September 24 to 26,…

    Read more

  • UPDATED: Traffic Update: Pedestrian access change between 62A Avenue and Fraser Highway 

    Posted September 1, 2026 – This is an update to the notice posted on August 19, 2026.  To support guideway installation as the launching gantry moves east, a pedestrian access change will be in effect until September…

    Read more